A Step Towards Connecting Uran With Mumbai: CR Launches Open Web Girders for Nerul/Belapur-Uran Project

The launching of girders is a complex job considering the line crossing with Panvel-Jasai-JNPT line which handles heavy container traffic and Dedicated Freight Corridor line is also under construction from JNPT to Panvel along the alignment.

A Step Towards Connecting Uran With Mumbai: CR Launches Open Web Girders for Nerul/Belapur-Uran Project
SHARES

Despite the coronavirus challenges, Central Railway has launched two 61-meter open web girders for Nerul/Belapur - Uran Project between Jasai & JNPT operating a block of 3 hours recently. It is a step towards connecting Uran with Mumbai Suburban Network. These 61-meter open web girders were fabricated at Central Railway Engineering Workshop, Manmad, transported and assembled at the launching site. Each girder weight is 232 MT (220 MT girder + 12MT lifting beam, holding bracket etc.)

The launching of girders is a complex job considering the line crossing with the Panvel-Jasai-JNPT line which handles heavy container traffic and the Dedicated Freight Corridor line is also under construction from JNPT to Panvel along the alignment. These girders were launched by 2 Crawler Road Cranes (1st crane= 600MT lifting capacity, 2nd crane = 500MT lifting capacity + 1 additional crane for emergency use of 750MT lifting capacity).

To ensure the safe lifting of girders, it was maintained verticality by a specially developed lifting frame. During lifting, the rotational movement was monitored by three inclinometers manufactured for this bridge. Inclinometers were used for the first time. Besides, Railway’s own structural testing unit was deployed by the bridge organization of Central Railway to capture the launching stresses in critical members.  Six stain gauges and two accelerometers were used for this and the launching was carried out without overstressing any members.  Down track web girder was successfully launched on 3rd July 2021 and Up track web girder was launched on August 12, 2021, taking 03:00 hrs Traffic and Power block each on Jasai-JNPT line. With this launching, the progress of the Phase-II of this line is in advanced stage. 

Works Carried Out During Lockdown

The major construction of this 4th corridor of Mumbai Suburban Corridor was superstructure work of Cover over Platform at Rajanpada station, foundation and sub-structure work at Nava-Sheva, Dronagiri and Uran stations, subway work at Uran, bridge foundation work, stressing and lowering of U-girder at the bridge.  The stretch of Kharkopar – Uran will have 5 stations, 2 major bridges, 46 minor bridges, 4 Road Under Bridges and 4 Road Over Bridges.  All precautions are taken to ensure the safety and health of the available labour. The project will help to accelerate the growth of Navi-Mumbai, by providing direct access between Uran town and Nhava-Sheva port and the newly developed area of Mumbai Metropolitan Region as well as Greater Mumbai.